Installation and debugging of organic fertilizer fermentation compost turning machine :

1. After the installation and assembly of all parts of the conveyor, we need to fix the chain plate of the conveyor in place to ensure that all legs, columns and platforms of the conveyor are fixed with chemical anchors. This step is very important. Only when the equipment is relatively stable, can it play a better role, so we should do a good job in this respect.

2, after one step can not be loosened, but also check all the bolts, do a good job of fixing, to ensure that each screw is fixed. Improper screw fastening may cause danger.

3. When dragging the shaft, the three shafts of the driving drum must be perpendicular to the vertical center line of the drum, otherwise the rotation is not flexible, so the three shafts need to be checked clearly, which is also a very important item.

4, need to check the conveying chain plate tension. If we want to check the tension, we need a set of data. This is appropriate if the tension is between 1% and 1.5% of the length tension.

5. If there is a drawstring switch, it should be installed on one side of the equipment. The two switches are connected by wire rope, and the tightness can be adjusted by itself.

6, there is a switch, is the deviation switch. It can be mounted on either side of the head and tail. It is also installed in pairs. The location is in accordance with the instructions.

The durability and maintainability of the organic fertilizer fermentation compost turning machine are very important. Therefore, when organic fertilizer equipment stops being used, we must strictly do a good job of maintenance to ensure that the equipment can work better for us and bring better benefits. 